CHD Chemical Centrifugal Pump
Product inquiry: 0523-84832479Product introduction
The CHD small-flow, high-head multipurpose chemical process pump is a single-stage, single-suction horizontal pump for gas-liquid mixing and transfer, low-level lifting, unloading and high-pressure transfer where flow is low, head is high and suction conditions are difficult.
Product presentation
Product overview
The CHD pump is single-stage, single-suction, horizontal with axial suction and radial discharge, mounted on an OH2 centerline support. The suction is at the highest point of the casing; stored liquid buffers self-priming and brief periods without liquid, but does not establish continuous dry-running or long-term operation without liquid. The multipurpose single-stage impeller accommodates gas-liquid mixing and higher heads, while the volute and compound impeller are arranged to reduce axial and radial forces.
Construction and features
- Single-stage, single-suction horizontal pump with axial suction, radial discharge and OH2 centerline support.
- The suction is at the highest casing point, and stored liquid buffers self-priming and short dry-running periods.
- The multipurpose single-stage impeller supports gas-liquid mixing and higher-head duty.
- The volute and compound impeller are matched to reduce axial and radial forces and improve running stability.
- A mechanical seal selected for the duty reduces air ingress and helps maintain suction vacuum.
Performance parameters (including materials)
Series reference ranges
| Parameter | Symbol | Value | Unit |
|---|---|---|---|
| Flow | Q | 1.6~20 | m³/h |
| Head | H | 60~320 | m |
| Speed | n | 2900 | r/min |
| Working pressure | P | 2.5~5 | MPa |
| Working temperature | T | -80~+350 | ℃ |
| Materials | — | 304, 304L, 316, 316L, 904, 904L, Hastelloy, titanium alloy, 2205, 2507, ZG25, 2Cr13, etc | — |
Note: These are series reference ranges. Refer to the selected model and supplied technical documentation for actual parameters.
Applications
The series is suitable for low-flow, high-head duties with difficult suction conditions:
It handles clean liquids and liquids with a viscosity of up to 50°E.
For some low-flow, high-head duties it can replace vacuum pumps, high-pressure pumps, self-priming pumps or long-shaft vertical pumps; confirm the actual substitution against the duty and selected model.
- Gas-liquid mixing and transfer
- Low-level lifting
- Unloading
- High-pressure transfer
Design and selection boundaries
Confirm the following boundaries against the actual duty during selection and use:
- The material list is a series option range; confirm the actual material for the selected model and duty.
- Performance parameters are series ranges. Confirm the actual flow, head, operating point, materials and seal configuration against the selected model and supplied technical documentation.
- OH2 centerline support, the highest-point suction and casing storage are structural boundaries of the series. Brief liquid-loss buffering does not permit continuous dry running or long-term operation without liquid.
- The handled liquid must be clean, with a maximum viscosity of 50°E. Confirm suitability for the actual medium.
- For selected low-flow, high-head duties, the pump can replace vacuum, high-pressure, self-priming or long-shaft vertical pumps. Compare each application against the selected model and technical agreement.
Confirm final parameters and construction against the selected model and supplied technical documentation.
Product information
| Model designation | CHD Chemical Centrifugal Pump |
|---|---|
| Catalog category | Chemical Centrifugal Pump |
Related questions
How is the duty point of a chemical centrifugal pump determined?
Build the system curve from static head, piping loss, equipment differential pressure and pressure conditions at target flow, then find its intersection with the exact pump curve.
Without the exact curve, material list and seal configuration, only the review method can be stated; final size, life or operating outcome cannot be confirmed.
What should be confirmed before selecting or working on pumps for corrosive, flammable, explosive, toxic or volatile media?
Obtain the SDS and complete duty first, identify corrosion, toxicity, fire/explosion, volatility, reactivity and exposure routes, then review wetted materials, containment/disposal, hazardous-area equipment, monitoring, emergency and personnel controls separately. A pump-family name does not establish risk control.
The project owner or responsible team must confirm site safety through professional risk assessment, relief and disposal design, hazardous-area equipment compliance, rescue arrangements and medical and occupational-health requirements.
Which equipment information is needed when requesting an operation manual?
Provide the complete model and model suffix, a clear nameplate photo, order or serial information, current configuration and required language. If the unit has been modified, describe the change so the manual is not matched from the series name alone.
An unregistered file requires public-release approval before it is shared. A filename, product photo or similar model cannot replace complete equipment-identity and revision checks.
What is the minimum data set for pump selection and enquiry?
Provide medium composition, concentration, density, viscosity and temperature; normal/minimum/maximum flow and head; suction, discharge and system pressure; available NPSH; solids or particle data; installation arrangement and space; power supply; and environmental conditions including indoor/outdoor location, temperature/humidity, altitude and hazardous-area classification.
The selection-input checklist gathers process and equipment information. Process design, piping calculations, final material configuration, hazardous-area suitability review and final quotation require the complete project package, and every missing field must remain explicitly open.
What should be checked first for the foundation and installation space?
First confirm foundation dimensions, anchor locations, load capacity and level from the order drawing. Then isolate the unit from adjacent-machine vibration and retain access for lifting, motor removal, inspection and disassembly.
Civil calculations, piping stress analysis, lifting plans, electrical codes, site safety approval and order drawings must be confirmed by the responsible disciplines and project documents. Dimensions from a similar model must not replace order drawings.
Which pumps require coupling-alignment checks?
Use the sectional drawing to identify direct drive, a separate coupling or a vertical shaft arrangement. Apply the model-specific alignment procedure only to the relevant connection; one tolerance does not fit every pump.
Alignment tolerance, jog duration and electrical steps must be determined for the exact model and site procedure. Perform a rotation check only after energy control, guarding and site authorization are complete.
Why is one start-up valve arrangement unsuitable for every pump?
Conventional centrifugal, self-priming and submerged pumps, as well as magnetic-drive pumps with different circulation paths, have different suction states, venting paths and permissible flow ranges. Valve positions must match the exact model and system control logic.
Remote start-up must follow the site authorization procedure. Valve positions, vent cycles and closed-valve duration must be determined from the matching manual revision and site procedure, and must not be transferred across models.
Which signals should be monitored during normal pump operation?
As configured, record flow, suction/discharge pressure, current, speed or frequency, vibration, sound, bearing or critical-point temperature, plus level, flushing, cooling and alarm states.
The site team must confirm continued operation through interlock settings, instrument calibration, root-cause analysis and maintenance permits. Do not restart until the cause and safety conditions are confirmed.
What must be completed before maintenance or disassembly?
Follow site procedure for shutdown, energy isolation, valve locking, depressurization, cooling, draining, flushing or decontamination, and verify that unintended start is prevented. Hazardous media also require the applicable work permit and personal protection.
Do not substitute drawings, part dimensions or materials from a similar model. A single symptom cannot establish root cause or a replacement part without site inspection.
How are wetted materials selected for a chemical centrifugal pump?
Use full composition, concentration, temperature, contaminants and cleaning phases to review casing, impeller, shaft, seal, lining and gasket materials separately.
Without the exact curve, material list and seal configuration, only the review method can be stated; final size, life or operating outcome cannot be confirmed.